Example scenario

Can the tool change wait until changeover?

The changeover is a candidate when the insert has enough life for the remaining cuts and the stop allows time to fit and verify its replacement.

A tool replacement could share a planned stop

The next product changeover starts in 43 minutes. The turning insert is nearing its replacement point, and only part of that interval will be spent cutting.

How it works

  1. Use Tool Manager to identify the mounted tool and review the offset history at that position. The tooling engineer assesses remaining life from the shop's inspection and usage records.
  2. Using the current order schedule, count the operations that still need this insert and estimate their cutting time. The 43 minutes until changeover include time when the insert is idle.
  3. Check the duration of the changeover against the time needed to fit and verify the replacement. The production planner decides when to stop. Scheduling against tool condition is on Qynetic Planner's roadmap.

How to interpret the result

Allow for uncertainty in the tool life estimate. If recent wear readings put the replacement criterion within reach before the final cut, schedule an earlier change. Recheck the estimate if the order sequence changes.